Project Details

Eskom PDP

Mkhulu-EDP

March 2014 – July 2015

The Duvha-Kusile 400 kV transmission line deviation project was completed on behalf of Eskom PDP between March 2014 and July 2015. Mkhulu Electro Distribution Projects (Pty) Ltd. undertook the project, which entailed deviating the transmission line for roughly 12 kilometers to enable mining activities connected to the coal supply for the Kusile Power Station.

The project’s scope of work comprised the installation of 32 towers, including 520B, 518H, 518C, and 518D towers. This necessitated extensive planning and coordination to guarantee that the project was done safely and within the time range specified.

The installation of a new tower beneath the old transmission line was one of the project’s major problems. This required meticulous planning and execution to guarantee that no existing infrastructure was damaged and that the new tower was built to the requisite specifications.

Mkhulu Electro Distribution Projects (Pty) Ltd. collaborated closely with Eskom PDP throughout the project to ensure that all safety and quality criteria were met. The project was completed satisfactorily, and the transmission line deviation allowed mining operations to continue while ensuring a consistent supply of power to the Kusile Power Station.

Hard tasks were :

  • Assisting senior consultants projects first lead sources support sales..
  • Share best both practices and knowledge
  • Assisting senior consultants projects first lead sources support sales..
  • Share best both practices and knowledge

The Challenge :

There were several challenges that the project team may have faced during the erection of 69 towers and stringing 42 kilometers of the line for Eskom in 2005. Some of these challenges could include:

  • Terrain: Tower erection and line stringing may have been harder in rocky or mountainous terrain.

  • Weather: Weather may have hampered the project. Rain or heavy winds could have slowed operations, making project deadlines impossible.
  • Safety: Working with high-voltage power transmission cables requires safety. The team may have struggled to teach and equip project personnel safely.

The Result :

To overcome these challenges, the project team may have implemented several strategies, including:

  • Planning and preparation: The team may have analyzed the site to discover topographical or weather issues that could affect the project. They may have also trained and outfitted workers with safety gear to work safely on the job.
  • Flexibility: The crew may have added time to the project plan for weather or terrain difficulties. They may have been adaptable to shifting work situations.
  • Collaboration: Transdeco, the main contractor, and Mkhulu Electro Distribution Projects cc, the subcontractor, may have collaborated to execute the project on schedule and within budget.

R4m

Total Cost

4.5%

Cost Reduce

100%

Completed

A business strategy is the means by which it sets out to achieve its desired forward thinking team looking for talent like you and make your dream come true have ideas, goals.

Out cases

Related Projects

Views: 42